Victoria Pearce, Support & Development Manager from the C.U. Phosco Contract Services Division, guides you through the three stages of our High Mast installation process: civils, the electrical installation and the installation of the High Mast itself.
Raising the High Mast is the final stage, but there’s a lot of planning and preparation that comes before it.
CIVILS
The civils team carries out any geotechnical surveys needed and designs the foundation base to suit the ground conditions. They then build the foundations to that specification. This includes arranging the concrete delivery and installing steel reinforcement cages where the design calls for them. Once complete, the High Mast foundations are ready for the mast to be installed.
ELECTRICAL INSTALLATION
Next comes the electrical installation, including feeder pillars and new cabling. This is often completed before the High Mast arrives, so all the electrical connections are ready in advance.
HIGH MAST INSTALLATION
Our masts are made in our own factory at Westgate, Cleckheaton, so we can control lead times and any special requirements. Once on site, the mast is assembled and rigged at ground level, our in-house lifting team then lifts it onto the foundation studs.
With the mast in place, our electrical team builds the carriage, fits and wires the lanterns, and sets the cables onto the winch.
The team then raises the carriage for the first time. This is the critical moment: the chain and bobbins must be set correctly so that the carriage can be raised and lowered properly in the future.
Once the carriage is docked, the panel is energised and tested, and the lights are switched on. Finally, the crane is de-rigged and the site is left clean and tidy, completing the installation.
Find out more about the C.U. Phosco Contract Services Division here or get in contact with the team.